Finishing process

Stage 0

Process
preparation

  • Determination of the final bill of materials, assistance in the possible selection of alternative materials
  • Determining the schedule of orders, works, payments
  • Signing the contract
  • Start of procurement of materials and equipment items

Stage 1

Preliminary work -
coordination of works

  • Covering windows, doors, other elements requiring protection
  • Replacement of the insert in the front door
  • Checking the quality of the screed – a decision on the possible need to level it, strengthen it
  • Measurement of door openings, ordering doors Coordination of the implementation of additional installations by cooperating companies (ventilation, recuperation, air conditioning, intelligent systems, etc.).
  • Demolition of walls, dismantling of the floor (in case of renovation)
  • Putting up new walls according to the project

Stage 2

Preliminary work -
coordination of works

  • Implementation / alteration of plumbing central heating and electrical installations
  • Installation of flush-mounted components (water, lighting, concealed door frames, etc.)
  • Execution of self-leveling screeds
  • Suspended ceilings, plasterboard buildings
  • Plastering

Stage 3

Preliminary work -
coordination of works

  • Installation of tiles, making grout
  • Installation of bathtubs, shower trays, ceramic parts and fixtures
  • Installation of stucco
  • First painting
  • Bringing in wood/laminate/vinyl flooring(acclimatization of the material)
  • Installation of the floor
  • Installation of wallpaper
  • Installation of curtain rods
  • Installation of technical lighting

Stage 4

Preliminary work -
coordination of works

  • Coordination of carpenters, upholsterers
  • Coordination of measurements and assemblies for accompanying services, e.g., stone countertops, household appliances

Stage 5

Preliminary work -
coordination of works

  • Second painting
  • Installation of the remaining ceramics and fittings, laying silicones
  • Connections of household appliances
  • Installation of other technical and decorative lamps
  • Installation of doors, handles, locks and skirting boards
  • Installation of electrical fixtures
  • Bringing in free-standing furniture
    (included in the list)
  • Installation of handles, paintings, mirrors
    (included in the list)
  • Cleaning of the premises including window cleaning
  • Hanging of curtains, drapes, blinds, shutters

Stage 6

Completion of works
and transfer of the premises to the owners

  • Cleaning of the premises including window cleaning
  • Hanging of curtains, drapes, blinds, shutters
  • Decoration, laying out carpets, setting up movable furniture