Finishing process
Stage 0
Process
preparation
- Determination of the final bill of materials, assistance in the possible selection of alternative materials
- Determining the schedule of orders, works, payments
- Signing the contract
- Start of procurement of materials and equipment items
Stage 1
Preliminary work -
coordination of works
- Covering windows, doors, other elements requiring protection
- Replacement of the insert in the front door
- Checking the quality of the screed – a decision on the possible need to level it, strengthen it
- Measurement of door openings, ordering doors Coordination of the implementation of additional installations by cooperating companies (ventilation, recuperation, air conditioning, intelligent systems, etc.).
- Demolition of walls, dismantling of the floor (in case of renovation)
- Putting up new walls according to the project
Stage 2
Preliminary work -
coordination of works
- Implementation / alteration of plumbing central heating and electrical installations
- Installation of flush-mounted components (water, lighting, concealed door frames, etc.)
- Execution of self-leveling screeds
- Suspended ceilings, plasterboard buildings
- Plastering
Stage 3
Preliminary work -
coordination of works
- Installation of tiles, making grout
- Installation of bathtubs, shower trays, ceramic parts and fixtures
- Installation of stucco
- First painting
- Bringing in wood/laminate/vinyl flooring(acclimatization of the material)
- Installation of the floor
- Installation of wallpaper
- Installation of curtain rods
- Installation of technical lighting
Stage 4
Preliminary work -
coordination of works
- Coordination of carpenters, upholsterers
- Coordination of measurements and assemblies for accompanying services, e.g., stone countertops, household appliances
Stage 5
Preliminary work -
coordination of works
- Second painting
- Installation of the remaining ceramics and fittings, laying silicones
- Connections of household appliances
- Installation of other technical and decorative lamps
- Installation of doors, handles, locks and skirting boards
- Installation of electrical fixtures
- Bringing in free-standing furniture
(included in the list) - Installation of handles, paintings, mirrors
(included in the list) - Cleaning of the premises including window cleaning
- Hanging of curtains, drapes, blinds, shutters
Stage 6
Completion of works
and transfer of the premises to the owners
- Cleaning of the premises including window cleaning
- Hanging of curtains, drapes, blinds, shutters
- Decoration, laying out carpets, setting up movable furniture